Anderson County
Palestine crews will be performing overlay on FM 2419. Expect lane closures with flaggers controlling traffic.
Anderson County construction projects updates:
US 175 Widening Project
- Limits: From 0.4 miles SE of SH 155, SE to Cuney
- Contractor: Big Creek Construction, LTD
- Cost: $55.5 million
- Anticipated Completion Date: Spring 2026
The contractor is scheduled to work on the eastbound side, constructing driveways and ditches. Crews will also continue work on the new rail on the westbound bridge. They will also set panels on the new eastbound bridge, as well as finalizing ditches and slopes. The contractor is also planning to work on roadway elements involving new pavement and road surface work in the westbound lanes. The project consists of expansion to a four-lane roadway with new bridges across the Neches River.
US 79 Truck Parking Area
- Limits: From 2.2 Mi E of FM 645 in Palestine
- Contractor: FNH Construction, LLC
- Cost: $664,000
- Anticipated Completion Date: Major items of work have been completed.
The contractor is awaiting final acceptance. The project includes concrete curb and gutter, earthwork, and drainage improvements.
Gus Engeling Texas Parks and Wildlife
- Limits: Roads and parking lot within Gus Engeling Wildlife Management area
- Contractor: Reynolds & Kay, LTD
- Cost: $171,000
- Anticipated Completion Date: Major items of work have been completed.
The contractor is awaiting final acceptance. The project includes surface treatment, pavement striping, and drainage improvements.
Cherokee County
Jacksonville crews are scheduled to perform overlay on FM 13 from SH 42 to Loop 571. Expect lane closures. Another crew will be widening FM 1798 from US 79 to FM 2867. Expect lane closures with flaggers controlling traffic.
Cherokee County construction projects updates:
US 175 Widening Project
- Limits: From 0.5 miles E of the Anderson County line (CR 3509) to FM 347 in Jacksonville
- Contractor: A.L. Helmcamp, INC.
- Cost: $168 million
- Anticipated Completion Date: Fall 2028
The following county road intersections will be closed within the project limits:
- FM 855 intersection: This will begin the week of May 5. Traffic will use the posted FM 855 detour route by taking US 175 east to US 69 north.
- CR 3410 intersection: local traffic will need to use the detour route for FM 855.
- CR 3416 intersection: local traffic will need to use the detour route for FM 855.
The contractor will begin finalizing asphalt grades at the intersection of FM 855. Also, the contractor will continue to work on the westbound roadway elements in preparation of switching traffic through Cuney. The contractor will also continue working on bridge elements, setting deck panels, clearing utility items, and building storm drain systems. Motorists should use caution when traveling through the area. The speed limit is reduced to 55 mph throughout the project limits. The project consists of expansion to a four-lane roadway with new bridges, grading, asphalt, drainage structures, pavement markings, and signage.
SH 204
- Limits: From SH 110 to the Rusk County line
- Contractor: Madden Contracting Company, LLC
- Cost: $22.5 million
- Anticipated Completion Date: Spring 2025
This project consists of adding a super-two highway section. This week, the contractor is scheduled to begin work on culverts, embankment, and cement treating the subgrade. Crews will also install and maintain SW3P measures. The contractor will also resume excavation, embankment work, and drainage on the east end. Motorists should drive with caution in the work zone. Lane closures are anticipated.
FM 2339 – SH 110
- Limits: 2.7 miles north of Rusk
- Contractor: Red Barron
- Cost: $1.6 million
- Anticipated Completion Date: Spring 2025
This project is a change order to a bridge preventative maintenance project that consists of installing a temporary soil nail wall and a permanent retaining wall to address slope failure on SH 110. Crews are scheduled to construct the permanent retaining wall. No lane closures are anticipated. Motorists should drive with caution when work is in progress.
US 69 and FM 2493 Grade Separated Interchange Realignment – SH 110
- Limits: US 69 – From 0.5 mi N of FM 2493 W to 0.5 mi south of FM 2493 E
FM 2493 – From 0.3 mi south of FM 344 to US 69 near Bullard
- Contractor: East Texas Bridge, Inc.
- Cost: $38.5 million
- Anticipated Completion Date: Spring 2027
The contractor is scheduled to work on storm sewer installation on FM 2493 east. When that work is complete, the contractor is scheduled to perform dirt work. Work could also begin on Old Jacksonville Rd. near Bullard High School. No lane closures are anticipated. Motorists should drive with caution. The project consists of a grade separated interchange and realignment of FM 2493 West of US 69.
US 69 Safety Improvement
- Limits: US 69 limits from FM 241 to 1.11 miles north of FM 851
- Contractor: Highway 19 Construction, LLC
- Cost: $3.85 million
- Anticipated Completion Date: Spring 2025
When work is complete on SH 31 in Smith County, crews will move to US 69 to begin prep work for the mow strip. Lane closures at not anticipated. Motorists are encouraged to drive with caution. The project consists of safety improvements consisting of the installation of a median cable barrier.
SH 204
- Limits: From SH 110 to the Rusk County line
- Contractor: Madden Contracting Company, LLC
- Cost: $22.5 million
- Anticipated Completion Date: Spring 2025
This project consists of adding a super-two highway section. This week, the contractor is scheduled to begin work on culverts, embankment, and cement treating the subgrade. Crews will also install and maintain SW3P measures. Motorists should drive with caution in the work zone. Lane closures are anticipated.
FM 2339 – SH 110
- Limits: 7 miles north of Rusk
- Contractor: Red Barron
- Cost: $1.6 million
- Anticipated Completion Date: Spring 2025
This project is a change order to a bridge preventative maintenance project that consists of installing a temporary soil nail wall and a permanent retaining wall to address slope failure on SH 110. Crews are scheduled to construct the permanent retaining wall. No lane closures are anticipated. Motorists should drive with caution when work is in progress.
US 69 and FM 2493 Grade Separated Interchange Realignment – SH 110
- Limits: US 69 – From 0.5 mi N of FM 2493 W to 0.5 mi south of FM 2493 E
FM 2493 – From 0.3 mi south of FM 344 to US 69 near Bullard
- Contractor: East Texas Bridge, Inc.
- Cost: $38.5 million
- Anticipated Completion Date: Spring 2027
The contractor is scheduled to work on storm sewer installation on FM 2493 east. When that work is complete, the contractor is scheduled to perform dirt work. Work could also begin on Old Jacksonville Rd. near Bullard High School. No lane closures are anticipated. Motorists should drive with caution. The project consists of a grade separated interchange and realignment of FM 2493 West of US 69.
US 69 Safety Improvement
- Limits: US 69 limits from FM 241 to 1.11 miles north of FM 851
- Contractor: Highway 19 Construction, LLC
- Cost: $3.85 million
- Anticipated Completion Date: Spring 2025
When work is complete on SH 31 in Smith County, crews will move to US 69 to begin prep work for the mow strip. Lane closures at not anticipated. Motorists are encouraged to drive with caution. The project consists of safety improvements consisting of the installation of a median cable barrier.
Henderson County
Athens crews are scheduled to perform base repair and overlay on FM 314, south of Brownsboro, as well as FM 1803. Expect daytime lane closures with flaggers controlling traffic.
Henderson County construction projects updates:
SH 198 Bridge Project
- Limits: At the Clear Creek Bridge a mile north of FM 3054 to 0.1 mile north of CR 2830
- Contractor: Copasa Inc.
- Cost: $30.4 million
- Anticipated Completion Date: Major items of work have been completed.
The contractor is awaiting final acceptance. The project includes replacing bridges and approaches, grading, structures, base and surface work, retaining walls, curbs and gutters, fencing, and striping.
FM 316 Rehabilitation
- Limits: From FM 1861 to US 175
- Contractor: Baker & Company Construction, LLC
- Cost: $7.9 million
- Anticipated Completion Date: Major items of work have been completed.
The project is in time suspension and awaiting final acceptance. The project includes pavement reconstruction, structures, pavement markings and signs.
FM 315 Rehabilitation
- Limits: From FM 3079 to FM 317
- Contractor: Big Creek Construction, LTD
- Cost: $1.9 million
- Anticipated Completion Date: Major items of work have been completed.
The contractor currently performing edge work at various locations throughout the project limits. There should be no impact to traffic. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
- Limits: From Ben Belt Fr. To S Loop 7 ramps
- Contractor: 3LW Civil, LCC
- Cost: $2.6 million
- Anticipated Completion Date: Summer 2025
The contractor is placing concrete for the sidewalks and driveways. Motorists should expect lane closures while work is in progress. This project includes sidewalk and pedestrian lane improvements.
SH 19 Super 2 Project
- Limits: From 0.3 Mi. S of FM 1861 (Van Zandt C/L) S to 0.1 Mi. N of SL 7 in Athens (Watson)
- Contractor: Big Creek Construction LTD
- Cost: $20.8 million
- Anticipated Completion Date: Summer 2026
The contractor is scheduled to work on cross-structures and roadway widening for the northbound lane. The speed limit is reduced to 60 mph throughout the project limits. This project includes adding a passing lane in each direction at multiple locations. It also includes grading, drainage structures, pavement markings, and signage.
BUS 31 Rehabilitation
- Limits: From BUS 19 to SL 7
- Contractor: Big Creek Construction LTD
- Cost: $8.1 million
- Anticipated Completion Date: Winter 2025
Nighttime milling operations have begun. Motorists should expect lane closures. The project includes removal of current surface, base repairs, resurfacing, striping, and signage. Traffic should use caution when traveling through the work zone at night and expect pavement striping operations during the day.
Smith County
Smith County crews will have one crew on FM 15 performing sealcoat prep. Expect lane closures with flaggers controlling traffic. A second crew is scheduled to perform ditch maintenance at various locations. Also, crews will apply herbicide at various locations throughout the county.
Smith County construction projects updates:
US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)
- Limits: Cumberland Road to .45 miles north of FM 346
- Contractor: Drewery Construction Company, INC
- Cost: $5.8 million
- Anticipated Completion Date: Spring 2025
The contractor is scheduled to widen at the R-Cuts as well as bringing in embankment to level-up the center median. They will also cement treat the subgrade. Lane closures are expected. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at FM 2813 intersection.
SH 31 Safety Improvement
- Limits: SH 31 (Smith Co) limits from the Neches River bridge to 0.051 miles west of Toll 49
- Contractor: Highway 19 Construction, LLC
- Cost: $3.85 million
- Anticipated Completion Date: Spring 2025
The contractor is scheduled to complete the placement of the new barriers near the rest area. Crews are also scheduled to begin demolition of the existing barrier near Toll 49 in Tyler. Motorists should drive with caution. Lane closures are expected on SH 31. This project consists of safety improvements consisting of backfill and topsoil operations. No lane closures are expected.
I-20 Frontage Road at SH 155
- Limits: Westbound off ramp at SH 155 from intersection to 600 ft toward I-20
- Contractor: FNH Construction, LLC.
- Cost: $600,000
- Anticipated Completion Date: Major items of work have been completed.
The contractor has no work scheduled. No lane closures expected. Project consists of resurfacing the roadway, pavement markings, signage, and illumination.
FM 2493 Widen Non-Freeway
- Limits: FM 346 in Flint, south to 0.3 miles south of FM 344
- Contractor: Longview Bridge and Road LTD
- Cost: $52 million
- Anticipated Completion Date: Spring 2027
This project consists of widening the existing non-freeway roadway. Utility relocations are in progress.
County Bridge Replacements
- Limits: CR 35 bridge at Hitts Creek Trib., CR 336 at Wiggins Creek, CR 411 at Prairie Creek Trib., CR 471 at Prairie Creek, CR 452 at Mill Creek, CR 411 at Caney Creek.
- Contractor: Baker & Company Construction, LLC
- Cost: $6.2 million
- Anticipated Completion Date: Winter 2025
This project consists of replacing existing bridge facilities and approaches. Construction is on-going at CR 452 over Mill Creek. The bridge will be closed for the duration of construction.
I-20 Bridge Maintenance
- Limits: I-20 bridges over CR 35 (Lavender Rd); FM 14; SH 155; FM 3311; CR 353; US 271; CR 3101 (Barber Rd); CR 3116 (Philpot Rd)
- Contractor: Olympus Painting Contractors, Inc.
- Cost: $3 million
- Anticipated Completion Date: Summer 2025
Lavender Rd. will have a lane closure under the I-20 bridge as crews continue cleaning, blasting, and painting. The project consists of cleaning and painting the existing steel bridge structures.
Legacy Trails Extension
- Limits: Stewart Park to Peete Elementary
- Contractor: THK Construction LLC.
- Cost: $3.5 million
- Anticipated Completion Date: Winter 2025
The contractor is scheduled to work on installing the retaining wall and backfilling. No lane closures are expected. Motorists should pay attention and drive with caution.
FM 16 Widening and Realignment
- Limits: 4 mi west of FM 849 east to US 69 in Lindale
- Contractor: Highway 19 Construction LLC
- Cost: $44.4 million
- Anticipated Completion Date: August 2025
The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. A traffic shift is currently in place through town. Traffic will be in two lanes during this phase of construction. The contractor is forming curb and gutter sections and installing inlet tops. The contractor is also planning on constructing a temporary retaining wall. Embankment installation is ongoing. Motorists are urged to drive with caution through the work zone.